| "We wish to compliment you on the excellent report rendered for the subject plant. The existing and additional new facilities were clearly presented. The breadth of data developed was extensive. And finally, the over-all organization and presentation of data was both practical and attractive. Many thanks."
Leo Fyer, Sr. E.E.
Alvarado Water Filtration Plant |
|
Seattle Office
16122 SE 266th Street
Covington, WA 98042
(253) 639-8535 P.
(253) 639-8685 F.
Fuhr@PowerStudies.com
San Francisco Office
2400 Third Street
San Francisco, CA 94107
(415) 828-0529
Tran@PowerStudies.com |
|
|
 |
 |
Boeing Company - Everett Facility
|
The Boeing facility in Everett, Washington is the main production facility for Boeing commercial airplanes in the Pacific Northwest. Here, the world's largest commercial aircraft (747, 767 and 777) are manufactured in the world's largest building. The building has grown over the years to enclose 472 million cubic feet of space. Its footprint covers 98.3 acres.
The plant power distribution system is a 15 kV system with over ten medium voltage substations. The facility has over 225 low voltage substations. Power Systems Engineering performed short circuit and protective device coordination studies. We also provided an ACCESS database that contains all of the substation data and breaker settings. We have also performed harmonic / power quality and motor starting studies at this facility.
|
 |
| Project Information |
| Study Performed |
Short circuit and Protective device coordination |
| # of Nodes |
1200 |
| Devices plotted |
467 |
| Time current sheets created |
89 |
|
< Back To Portfolio |
|
| |
|