Puget
Sound Energy, Auburn Power Factor Capacitor Bank Harmonic Resonance
Investigation
|
|
Puget Sound Energy is a utility company serving
Western
Washington. They installed two capacitor banks at the Boeing Auburn Plant
main substations. The purpose of these capacitors was to correct the
power factor at the Auburn Plant. There were concerns about the potential
of harmonic sources and possible resonance problems.
Puget Sound Energy hired Power Systems Engineering to perform a harmonic
analysis study to determine the resonance point of the capacitors and
transformers. The transformers and capacitors together acted as tuned 5th
harmonic filters. They provide a low impedance path for 5th harmonic
currents in the utility distribution system.
Power Systems Engineering's engineer recommended that the capacitor banks
be de-tuned by removing a portion of the capacitance. This eliminated the
problem and cleaned up the voltage sine wave and lowered the %THD.
|
 |
 |
Project Information |
 |
| |
Project
|
Boeing - Auburn
Power Factor Capacitor Bank Harmonic Resonance Investigation
|
|
|
|
Client
|
Puget Sound Energy - Bellevue, Washington
|
|
 |
|
 |
|
| Puget Sound Energy, Feeder to Crystal Mountain Ski Resort Harmonic
Investigation |
|
Puget Sound Energy is a utility company
serving Western Washington. They noticed that the voltage had an
excessive amount of harmonics and the %THD exceeded the IEEE-519
guidelines.
Puget Sound Energy hired Power Systems Engineering, to model their
distribution system from the Greenwater Substation to the Crystal
Mountain Ski Resort. The purpose of this study was to determine why the
voltage distortion was so high at the location.
The engineers at Power Systems Engineering found that due to the
underground cable capacitance and system transformers, the system was
tuned to the 5th harmonic. The ski resort has numerous variable speed
drives that produce 5th harmonic currents. These currents along with
the system tuned to the 5th harmonic caused the high %THD.
Power Systems Engineering worked with the utility to redesign the
distribution system and to shift the system resonant point to an even
number.
|
 |
 |
Project Information |
 |
| |
Project
|
Feeder to Crystal Mountain Ski Resort Harmonic
Investigation
|
|
|
|
Client
|
Puget Sound Energy - Bellevue, Washington
|
|
 |
|
 |
|